Projects

Long Term Accommodation Project (LTAP) - Early Works for Ettouk Island and Umm AL Anbar Island

Project Location – Upper Zakum Ettouk Island and Umm Al Anbar Island

Client –
ADNOC  Offshore

Main Contractor –
Venus Infrastructure Contracting LLC

The Engineering, Procurement & Construction (EPC) project scope included civil, mechanical, and electrical works to support new accommodation facilities. Civil works involve the construction of essential support buildings such as a kitchen, mess hall, recreation and laundry units, along with the refurbishment and relocation of an existing G+2 camp. It also includes demolition and removal of scrap materials to designated areas in Abu Dhabi, as well as site preparation activities like clearing, underground utility scanning, and topographic surveying. Mechanical works cover the installation of HDPE potable water and UPVC sewer networks, booster pumps, and firefighting systems with hydrants and hose reels. Electrical works include the supply, installation, and commissioning of Diesel Generators, associated distribution boards (Totalizing Panel, MDB, SMDBs), power and earthing cables, and fire alarm systems with FACP and detectors.

Replacement of Fuel Piping at Old Service Stations

Project Location – All Emirates in UAE 

Client –
ADNOC Distribution 

Main Contractor –
Venus Infrastructure Contracting LLC                                                                                      
The Engineering, Procurement & Construction (EPC) scope consisted of civil and MEP works with excavation in the tank area and along trenches to facilitate the replacement of fuel pipelines across 67 fuel stations throughout all Emirates. This includes backfilling, compaction, and reinstatement of surface features such as interlock paving and kerbstones, along with the casting of spill containment structures. The Mechanical works include the removal of the existing carbon steel fuel delivery pipeline and its replacement with double-wall polyethylene piping from the fuel tank to the dispenser. Additionally, the scope covers the supply and installation of dispenser sumps and a flame arrestor equipped with a Pressure Vacuum Relief Valve (PVRV) for the vent line.

Replacement of Foam pumps in Al Ain Zakher Terminal

Project Location –Zakher Terminal Al Ain 

Client –
ADNOC Distribution

Main Contractor –
Venus Infrastructure Contracting LLC 

The Engineering, Procurement & Construction (EPC) scope of works included both mechanical and instrumentation activities. The mechanical works involved the replacement of defective foam pumps at Al Ain Zakher Terminal foam stations 01, 02, and 03, including necessary modifications to upstream and downstream piping with stainless steel cladding. Additionally, filtration and cleaning of existing foam tanks at all three pumping stations were performed. The instrumentation works covered the supply and installation of strainers, differential pressure gauges, pressure transducers, pressure relief valves and pressure control valves, along with required modifications to the associated piping.

Supply, Installation and Commissioning of New Electromagnetic Flow Meters in Abu Dhabi Region

Project Location - Umm Al Nar Abu Dhabi 

Client –
TRANSCO,

Main Contractor –
Venus Infrastructure Contracting LLC 

The Engineering, Procurement & Construction (EPC) scope of works included comprehensive mechanical and instrumentation activities focused on the supply and installation of electromagnetic flow meters across key locations in the potable water distribution network, specifically at Taweela A1, Taweela B2, Unit 3, Unit 4, and Umm Al Nar pumping stations. These installations accommodated pipe sizes ranging from 600 mm to 1600 mm and involved all necessary shutdown operations to facilitate a safe and efficient implementation. Additionally, the scope encompasses modifications to the existing SCADA system to ensure proper integration of the new instrumentation, enabling accurate real-time monitoring and control of the water distribution system.

Al Reeman 02 Phase 03 Villas and Infrastructure – Residential Development

Project Location – Abu Dhabi 

Client –
ALDAR 

Main Contractor –
Nurol LLC OPC 

Scope of Works Includes Civil & Electro-mechanical Works: 

Mechanical Works:
Supply and installation of HDPE potable water networks with pipe sizes ranging from 80mm to 300mm, including associated fittings such as tee valve chambers, flow meter and flow control valve chambers, washout and air valve chambers, electromagnetic flow meters within flow meter chambers, ductile iron pipes, accessories, and fire hydrants. 

Electrical Works:
Supply and installation of sector measuring points, including GRP sector metering kiosks, along with all associated cabling and earthing works. 

Civil Works:
Excavation, sand bedding, backfilling, concrete encasement for road crossings, in-situ casting of valve chambers, pull box chambers, and protection slabs.

Mugharraq Port – Phase 2A – Infrastructure Works 

Project Location – Ruwais Port 

Client –
Abu Dhabi Ports Group

Main Contractor –
Al Ryum Cont. & General Transport LLC 

Scope of Works Includes Electro-mechanical & Instrumentation Works 

Electrical Works:
Supply, installation, testing, and commissioning of MCC panels, distribution boards, control panel earthing systems, and associated cabling. 

Instrumentation Works:
Supply, installation, testing, and commissioning of programmable logic controllers (PLCs), SCADA workstations, electromagnetic flow meters, pressure transmitters, flood detection systems, float switches, level transmitters, and instrumentation cabling. 

Mechanical Works:
Supply, installation, testing, and commissioning of submersible pumps, penstocks, macerators, ductile iron (DI) pipes and fittings, valves, Jib cranes, and surge vessels.

Riyad City South – Phase 04, Roads and Infrastructure Works, Potable water and Irrigation network

Project Location – Abu Dhabi 

Client –
ALDAR

Main Contractor –
Nurol LLC OPC 

The electro-mechanical works involved the supply and installation of potable water and irrigation networks using ductile iron (DI) pipes and fittings, with pipe sizes ranging from 80mm to 600mm. The scope included the installation of valves, line valve chambers, tee valve chambers, flow meter and flow control valve chambers, washout and air valve chambers, 14 electromagnetic flow meters housed within dedicated chambers, and 791 fire hydrants. The electrical works comprise the supply and installation of sector measuring points, including GRP sector metering kiosks, along with associated cabling and earthing works

Al Ain Stadium and Tunnel

Project Location – Al Ain 

Client –
Musanada /AADC 

Main Contractor –
BATCO 

The works consisted across storm water network and pumping station included the installation of ductile iron (DI) pipes up to DN500mm in size, along with valves and related accessories for the storm water pumping station and associated external works. Electromechanical works encompass pumps, MCC with automatic transfer switches (ATS), generators, flow meters, valves, DI piping, and GRP piping systems. Electrical works involved the installation of MCC panels, ATS units, generators, and associated cable laying. Mechanical works cover the installation of DI pipes and fittings, valves, flow meters, and pumps.

N – 14673.2 MIRFA C  

Project Location – Madinat Zayed, Abu Dhabi 

Client –
TRANSCO

Main Contractor –
METITO

The works consisted of fabrication and installation of cast iron (CI) piping and pumping station works. For the potable water network, the project involved fabrication, welding, and installation of carbon steel piping for water distribution pipelines, along with equipment installation at the pumping station. The work included carbon steel pipework up to 1600 mm in diameter, a 100 m³ surge vessel, and horizontal split case pumps.

Delma Port Marine Works North 

Project Location – Delma Island

Client –
Abu Dhabi Ports 

Main Contractor -
NMDC

The works consisted of electrical and street lighting installations. This involved the supply and installation of 14-meter-high light pole with single-arm LED luminaires, complete with required foundations and accessories. Electrical works cover all associated low-voltage (LV) cable networks from the substation, feeder pillars, SLCC, and street light control cabinets, including solar timers and earth pits.

Relocation of Existing Potable Water and Electrical Network at Jubail Island

Project Location - Jubail Island Abu Dhabi 

Client –
Jubail Island Investment Company

Main Contractor -
NMDC

The works consisted of electromechanical and infrastructure utilities. For the potable water network, the project involved supply, installation, testing, and tie-in of a DN225 main HDPE pipeline, using butt fusion welding and horizontal directional drilling to relocate the existing line. Works also included installation of ductile iron fittings inside valve chambers, isolation gate valves, air release valves, and removal of the existing HDPE pipeline. Electrical works covered the relocation of the electrical network, including installation of uPVC cable ducts in trenches and laying of 11 kV cables with joints and terminations.

EXPO 2020 Operations Pavilions

Project Location – Dubai 

Client –
EXPO 2020

Main Contractor -
Spacemaker

The works consisted of electro-mechanical and utilities installations. For the Operations Pavilion, MEP works involved the supply and installation of MDB, SMDB, FDB panels, cables, lighting fixtures, switches, sockets, sanitary fittings, earth pits, earth rods, and accessories for MDB, SMDB, capacitor banks, and the building earthing system. The potable water system included supply and installation of uPVC and PPR piping along with water meters. The drainage network covered the supply and installation of uPVC drainage pipes and precast manholes.

The Address Fujairah Resort and SPA 

Project Location – Fujairah

Client –
Sharm Fujairah Real Estate

Main Contractor -
BATCO

The works consisted of comprehensive electro-mechanical and instrumentation works across potable water, sewerage, and irrigation pumping stations. For the Potable Water Pump Station, the scope covered installation of pumps (210 m³/hr at 6 bar), ductile iron piping, valves, fittings, and a pressure vessel, along with electrical and instrumentation works including distribution boards and cable laying. The Sewerage Pumping Station involved installation of pumps (321 l/s at 18 m head), ductile iron piping, valves, fittings, a lifting davit, macerator, and a 160 m³/hr odour control unit, as well as MCC panels, distribution boards, and instrumentation cabling. For the Irrigation Pumping Station, works included installation of pumps (48 l/s at 40 m head), DI piping, valves, fittings, and a 1400 GPM irrigation filter, along with associated MCC panels and electrical distribution systems.

Maintenance, Improvement and Upgrade of Hamad Bin Abdullah Road Al Fujairah

Project Location - Fujairah

Client –
Ministry of Infrastructure Development

Main Contractor -
BATCO

The works consisted of supply, installation, testing, and commissioning of storm water pumping stations and associated mechanical, pipeline, and electrical works. 

Storm Water Pumping Stations:
Installation of three pumping stations equipped with submersible pumps—eight units with a capacity of 832.7 m³/hr and four units with a capacity of 643 m³/hr. The scope also includes discharge pipeline works using GRP piping (up to DN700), installation of penstocks (DN600, DN800), gate valves, non-return valves (NRVs), and level instruments. 

Sewerage Network:
Installation of GRP sewer pipes (up to DN700), manholes, and connection to existing sewer manholes. 

Electrical and Electromechanical Works:
Installation of systems for three substations, including MCC panels, main distribution boards (MDs), capacitor banks, and power cables ranging from 4C x 10mm² to 1C x 630mm². Additional works include small power systems, air conditioning, NOVEC firefighting systems, and fire alarm systems for the substation buildings.

Saadiyat Island Infrastructure Projects P031 Marina District Deep Utilities

Project Location - Saadiyat Island

Client –
TDIC 

Main Contractor -
Nurol LLC

The project encompasses the execution of comprehensive infrastructure utilities, including irrigation, sewerage, pipeline relocation, and metering systems. 

Irrigation Network:
Supply, installation, testing, and commissioning of HDPE pipelines (up to 630mm diameter) using the open-cut method, and installation of a 630mm HDPE sea crossing pipeline (700 meters) via Horizontal Directional Drilling (HDD), using butt fusion welding. Electromechanical chamber works include Ductile Iron pipes and fittings, gate valves, air release valves, flow meters, washout valves, flow control valves, and accessories. 

Pipeline Relocation:
Supply, installation, testing, and tie-in works for DN250 HDPE main pipeline using butt fusion welding for the relocation of an existing line. Works include DI fittings inside valve chambers, isolation gate valves, air release valves, and removal of the existing pipeline. 

Metering System:
Supply and installation of flow meters up to DN500 in size. 

Sewerage Network:
Installation of a 315mm HDPE sewer force main using butt fusion welding and associated valve chambers. Installation of GRP and uPVC gravity pipelines (up to DN1400 and depths of up to 12 meters) between manholes, including tie-in works to the existing STP plant using the Non-Disruptive Method (NDM) for DN1400 pipeline.

Support Facilities for PTB Expansion FZ Crew Briefing and Operations Centre

Client – Dubai Aviation Engineering Projects Corporation

Project Location -
Al Maktoum International Airport

Main Contractor -
Spacemaker Dubai

The works consisted of supply and installation of Form 2 SMDBs, along with the supply, installation, testing and commissioning of Form 4b, Type-6 SMDBs. The works also covered associated LV cable installations. Additionally, the scope includes the supply and installation of a gate barrier system for parking management.

Central Island 580 Men Camp - Dining Hall Extension

Project Location – Upper Zakum Central Island

Client –
ZADCO

Main Contractor –
Spacemaker

The works consisted of supply and installation of a complete drainage network consisting of uPVC pipes and fittings in accordance with BS EN 1401-1, with sizes up to 315mm, along with precast concrete manholes. For the potable water network, the works involved the supply and installation of uPVC pipes and fittings as per BS 3505 standards, up to 200mm in diameter, including the installation of pumps and a pressure vessel. The electrical works covered the supply and installation of Main Distribution Boards (MDBs), Sub Main Distribution Boards (SMDBs), as well as associated power and earthing cable networks and the complete earthing system.

South Island AUP Camp – Rectification Works for Common Facilities

Project Location – Upper Zakum South Island

Client –
ZADCO

Main Contractor -
Spacemaker

The works consisted of supply and installation of uPVC pipes and fittings up to 315mm in diameter, along with the installation of precast concrete manholes for the building’s external drainage system. For the potable water network, the works involved supplying and installing uPVC pipes and fittings (as per BS 3505) ranging from 50mm to 200mm in diameter, including pumps and a pressure vessel. Additionally, the scope covers the supply and installation of a kitchen hood and chequered plates as part of the kitchen modification works.

West Island IP Temporary camp - Accommodation and Utility project

Project Location - Upper Zakum West Island

Client –
ZADCO

Main Contractor –
Spacemaker

The works consisted of supply and installation of uPVC pipes and fittings for the drainage network, in accordance with BS EN 1401-1, with pipe sizes up to 315mm, along with precast concrete manholes. For the potable water network, the works involved the supply and installation of uPVC pipes and fittings as per BS 3505 standards, with sizes up to 200mm, including associated pumps and a pressure vessel. The electrical works covered the supply and installation of Main Distribution Boards (MDBs), Sub Main Distribution Boards (SMDBs), power and earthing cabling, as well as the complete earthing system.

Supply & Installation of MEP Works at Central Island Camp Extension 

Project Location - Upper Zakum Central Island

Client –
ZADCO

Main Contractor -
Spacemaker

The works consisted of supply and installation of uPVC pipes and fittings for the drainage network, complying with BS EN 1401-1 standards, with sizes up to 315mm, along with precast concrete manholes. For the potable water network, uPVC pipes and fittings are supplied and installed as per BS 3505 standards, with sizes up to 200mm, including pumps and a pressure vessel. The irrigation network involved the supply and installation of uPVC pipes and fittings, also in accordance with BS 3505, up to 200mm in size. Sewer lifting station works covered mechanical and electrical installations, including pumps, valves, pipelines, and low-voltage panels. Electrical works comprise the supply and installation of Main Distribution Boards (MDBs), Sub Main Distribution Boards (SMDBs), power and earthing cabling, and complete earthing systems.

Camp Office and Accommodation Facility Project 

Project Location - Upper Zakum Central Island, West Island, South Island and North Island 

Client –
ZADCO

Main Contractor –
Spacemaker  (Central, West & South Island) & Leighton Contracting Abu Dhabi (North Island) 

The scope of works comprised comprehensive utility infrastructure installations. It included the drainage network, involving the supply and installation of uPVC pipes and fittings (BSEN 1401-1, up to 315mm in diameter) and precast concrete manholes. For the potable water network, the works cover the supply and installation of uPVC pipes and fittings (BS3505, up to 200mm), along with the installation of pumps and a pressure vessel. The irrigation network involves the supply and installation of uPVC pipes and fittings (BS3505, up to 200mm). Additionally, sewer lifting station works include the mechanical and electrical installation of pumps, valves, pipelines, and LV panels. The electrical scope includes the supply and installation of MDBs and SMDBs, as well as associated power and earthing cabling works.

MAFRAQ Hospital Package II Feeder Line for Irrigation System

Project Location - Mafraq, Abu Dhabi

Client –
SEHA

Main Contractor -
Al Habtoor Leighton Murray & Roberts

The Irrigation Feeder Network scope included comprehensive electromechanical works for the irrigation system. This involved the supply, installation, testing, and commissioning of HDPE main pipelines (up to 400mm diameter), along with ductile iron (DI) fittings, valves, and flow meters installed within valve chambers. The scope also covered the installation of a control panel for the irrigation system, GRP kiosks to house the flow meters, and all associated cable interconnections required for system operation and monitoring.

Piping and Electrical works for Camp Office and Accommodation Facilities at Hail Island

Project Location - Hail Island

Client –
ADNOC

Main Contractor -
NMDC Abu Dhabi

The scope of works comprised comprehensive utility infrastructure installations. It includes the drainage network, involving the supply and installation of uPVC pipes and fittings (BSEN 1401-1, up to 315mm in diameter) and precast concrete manholes. For the potable water network, the works cover the supply and installation of uPVC pipes and fittings (BS3505, up to 200mm), along with the installation of pumps and a pressure vessel. The irrigation network involves the supply and installation of uPVC pipes and fittings (BS3505, up to 200mm). Additionally, sewer lifting station works include the mechanical and electrical installation of pumps, valves, pipelines, and LV panels. The electrical scope includes the supply and installation of MDBs and SMDBs, as well as associated power and earthing cabling works.

TDIC - Saadiyat Island Tunnel - Museum Infrastructure

Project Location – Saadiyat Island, Abu Dhabi

Client –
TDIC, Consultant – CHSS

Main Contractor -
NUROL 

The Electromechanical works comprise the complete scope for multiple systems. The Ventilation System includes the supply, installation, testing, commissioning, and maintenance of a Tunnel Ventilation System equipped with 20 Jet Fans, along with all required cabling, control panels, and SCADA interface integration. The Drainage Network with Pumping Stations covers the supply, installation, testing, commissioning, and maintenance of storm water pumping stations, featuring 7 submersible pumps. 

The Electrical Works scope involves the supply and installation of control panels for both the drainage and ventilation systems, including necessary cable laying and terminations. The Mechanical Works include the supply, installation, testing, commissioning, and maintenance of two storm water pumping stations, with submersible pumps (7 Nos) and associated stainless steel piping (up to DN350) complete with valves and non-return valves (NRVs). 

Additionally, Instrumentation and SCADA Interface Work involves the supply and installation of ultrasonic level transmitters, float switches, and limit switches for valves, with full integration of instruments into the SCADA system.

Accommodation Relocation and Utility Project - Upper Zakum North Island 

Project Location – Upper Zakum North Island

Client -
NMDC

Main Contractor -
Spacemaker Abu Dhabi

The infrastructure utilities work consisted of Drainage Network, involving the supply and installation of uPVC pipes and fittings conforming to BSEN 1401-1, with pipe sizes up to 315mm, and the installation of precast concrete manholes. For the Potable Water Network, the works cover the supply and installation of uPVC pipes and fittings as per BS3505, with sizes up to 200mm, along with pumps and a pressure vessel. The Electrical Works scope includes the supply and installation of Main Distribution Boards (MDBs) and Sub-Main Distribution Boards (SMDBs), as well as associated power and earthing cable networks and earthing systems.

Cast House Mechanical Installation Package No. CM- 7264

Client – EMAL

Project Location -
Taweelah, Abu Dhabi

Main Contractor -
Larsen and Toubro

The works consisted of Pipeline Fabrication, Welding, and Installation comprising the supply, fabrication, welding, installation, testing, and commissioning of Carbon Steel (CS) piping up to DN600, Stainless Steel (SS) piping, and HDPE piping along with necessary fittings, accessories, and painting works. These installations support the potable water system, cooling water system, and pressurized air and gas lines for both existing and new cast house facilities. Additionally, the scope includes the relocation of HDPE pipelines for the potable water network with pipe sizes up to DN300.

DG Equipments at Arzanah Island
Project No. 890/ITT No FTCSU906713

Project Location - Arzanah Island

Client –
ZADCO

Contractor -
ADMMI

The electromechanical works involved the supply and installation of the fuel pipeline, GRP cable trays, earthing system, and 13.8kV cable laying, along with testing and commissioning of medium voltage (MV) cables.

Plant Wide – Underground Services at EMAL Contract No. 503406

Project Location – Taweelah Abu Dhabi

Client –
EMAL

Main Contractor –
Consolidated Contracting Engineering

The works consisted of installation across various networks: Storm water and drainage networks with RCC pipes up to DN2000 and UPVC pipes up to DN600, including all necessary tie-ins and manhole connections. Sanitary sewage networks involve installing UPVC pipes up to DN250 with connections to existing systems and manholes. Fire water networks cover the installation of FRP pipes up to DN300, carbon steel pipes with welding, wrapping, valves, and fittings. Potable water networks include installation of HDPE pipes (SDR9) up to DN300 and fittings. Pressurized sanitary sewage systems involve UPVC pipes and fittings up to DN200, including valves, tie-ins, and manhole connections. Pumped storm water works include UPVC pipes and fittings up to DN300 with valves and system tie-ins. Permeate service water systems consist of SDR 9 HDPE pipes and fittings up to DN300 with valves and accessories. Compressed air and natural gas networks involve carbon steel piping with welding up to DN600. Lastly, utility road crossing duct works include installation of UPVC road crossing ducts up to DN400 in size.

Al Ain Water Distribution Network, EPC Contract 6820 Pump Station at AARC

Project Location - Al Ain

Client –
TRANSCO

Main Contractor -
Torishima Pump Mfg. Co

The works consisted of pipeline fabrication, welding, and installation for the potable water distribution network. This includes fabrication, installation, and testing of FBE-coated carbon steel pipes and fittings up to 2200mm in diameter (supplied by the client). The work involves field welding of pipe joints, non-destructive testing (NDT) of the welds, and holiday checks on the carbon steel pipes to ensure coating integrity.

Southern Tunnel Crossing at Yas Island Development Project MEP Works

Project Location - Yas Island, Abu Dhabi

Client –
ALDAR

Main Contractor -
Taisei Corporation

The scope of electromechanical works includes the Tunnel Ventilation System, encompassing the supply, installation, testing, commissioning, and maintenance of 40 jet fans, along with all necessary cabling, control panels, and SCADA interface for system automation. The drainage network comprises the complete setup of three storm water pumping stations, which includes 16 submersible pumps, stainless steel pipework (up to DN350), valves, non-return valves (NRVs), level instruments, and flow meters for automatic tunnel drainage operation. The system also includes the connection of discharge lines to the existing drainage system via oil interceptors and bar screens. The electrical works involve the supply and installation of control panels for both the drainage and ventilation systems, as well as all associated cable laying and termination. Additionally, the instrumentation and SCADA interface scope includes the supply and installation of ultrasonic level transmitters, float switches, limit switches for valves, and integration of all instrumentation with the SCADA system.

Automation of Existing Water Supply System to Sh. Khalifa Palace Contract No. 3232

Project Location - Al Ain

Client –
TRANSCO

Main Contractor -
ASTRACO Construction

The works consisted of instrumentation and SCADA interface work along with electromechanical tasks. This involves the supply, installation, testing, and commissioning of control valves and an RTU shelter equipped with distribution boards (DB, SMDB, UPSDB) and an A/C sequence panel for remote SCADA operation. Additionally, the work covered the supply and installation of flow meters up to DN400 in size, along with other associated instrumentation.

F1 Race Track & Hotels AWCS, CS Pipe Installation Works

Project Location - Yas Island, Abu Dhabi

Client –
ALDAR

Contractor -
ENVAC Middle East

The works consisted of pipeline fabrication, welding, and installation works includes the installation of 5.89 km of 3LPE-coated mild steel pipelines for the automated waste collection system on Yas Island. This involved fabrication, fit-up, and welding activities. Additionally, a cathodic protection system is installed along 13.3 km, with exothermic welding of anodes at every 150 meters. Trench excavation works cover 4.6 km for laying the MS refuse pipes, including bedding, sand surrounding, compaction, warning tape installation, backfilling, and removal of surplus excavated material off-site. The project also includes the construction of 21 manholes with excavation works for inspection and maintenance of the waste collection system.

Palm Jumeirah Gateway Project – Towers & Car Park Podium

Project Location – Dubai

Client - Nakheel

Main Contractor - Taisei Corporation Dubai

The electromechanical works consisted of both mechanical and electrical tasks, including the supply and installation of cables and light fittings. The scope also includes the installation of a penstock measuring 2800x1600mm, a 1600mm duckbill check valve, GRP pipes and fittings up to 1800mm in diameter, along with the associated civil works.

Palm Jumeirah Gateway Project – Relocation & Extension of Existing Storm Water Drainage Line

Project Location – Dubai

Client –
Nakheel

Contractor -
Taisei Corporation

The works consisted of storm water drainage network works include earthwork excavation for pipe laying, including bedding, sand surrounding, warning tape installation, backfilling, compaction, and removal of surplus material. The scope also covers the installation of GRP pipes with diameters of 400mm, 1400mm, and 1600mm in trenches, including GRP lamination joints.

Shahama – Saadiyat Freeway Project, Package 2A, Electrical Works for the Bridges

Project Location - Yas Island, Abu Dhabi

Client –
ALDAR

Contractor -
Taisei Corporation

The works consisted of electrical works for bridges BC-3, BC-4, BC-5, BC-7, and BC-8 include the supply and installation of cables, junction boxes, and support systems. The scope covers the installation of 108 light poles and bridge lights, 3,942 meters of 6-way telephone ducts, and 1,902 meters of 6-way 22kV cable ducts (DN200). Additionally, navigational lights, day markers, and control panels are supplied and installed. The works also include the supply and laying of cables up to 16mm² over 6,050 meters and PVC conduits up to 100mm diameter totaling 3,170 meters.