Project
Location – Upper Zakum Ettouk Island and Umm Al Anbar Island
Client
–ADNOC Offshore
Main
Contractor – Venus Infrastructure Contracting
LLC
The Engineering, Procurement & Construction (EPC) project
scope included civil, mechanical, and electrical works to support new
accommodation facilities. Civil works involve the construction of essential
support buildings such as a kitchen, mess hall, recreation and laundry units,
along with the refurbishment and relocation of an existing G+2 camp. It also
includes demolition and removal of scrap materials to designated areas in Abu
Dhabi, as well as site preparation activities like clearing, underground utility
scanning, and topographic surveying. Mechanical works cover the installation of
HDPE potable water and UPVC sewer networks, booster pumps, and firefighting
systems with hydrants and hose reels. Electrical works include the supply,
installation, and commissioning of Diesel Generators, associated distribution
boards (Totalizing Panel, MDB, SMDBs), power and earthing cables, and fire
alarm systems with FACP and detectors.
Project Location – All Emirates in UAE
Client – ADNOC Distribution
Main Contractor – Venus Infrastructure Contracting LLC
The Engineering, Procurement & Construction (EPC) scope
consisted of civil and MEP works with excavation in the tank area and along
trenches to facilitate the replacement of fuel pipelines across 67 fuel
stations throughout all Emirates. This includes backfilling, compaction, and
reinstatement of surface features such as interlock paving and kerbstones,
along with the casting of spill containment structures. The Mechanical works
include the removal of the existing carbon steel fuel delivery pipeline and its
replacement with double-wall polyethylene piping from the fuel tank to the
dispenser. Additionally, the scope covers the supply and installation of
dispenser sumps and a flame arrestor equipped with a Pressure Vacuum Relief
Valve (PVRV) for the vent line.
Project
Location –Zakher Terminal Al Ain
Client
– ADNOC Distribution
Main
Contractor – Venus Infrastructure
Contracting LLC
The Engineering, Procurement & Construction (EPC) scope
of works included both mechanical and instrumentation activities. The
mechanical works involved the replacement of defective foam pumps at Al Ain
Zakher Terminal foam stations 01, 02, and 03, including necessary modifications
to upstream and downstream piping with stainless steel cladding. Additionally,
filtration and cleaning of existing foam tanks at all three pumping stations were
performed. The instrumentation works covered the supply and installation of
strainers, differential pressure gauges, pressure transducers, pressure relief
valves and pressure control valves, along with required modifications to the
associated piping.
Project Location - Umm Al Nar Abu Dhabi
Client – TRANSCO,
Main Contractor
– Venus Infrastructure
Contracting LLC
The Engineering, Procurement & Construction
(EPC) scope of works included comprehensive mechanical and instrumentation
activities focused on the supply and installation of electromagnetic flow
meters across key locations in the potable water distribution network,
specifically at Taweela A1, Taweela B2, Unit 3, Unit 4, and Umm Al Nar pumping
stations. These installations accommodated pipe sizes ranging from 600 mm to
1600 mm and involved all necessary shutdown operations to facilitate a safe and
efficient implementation. Additionally, the scope encompasses modifications to
the existing SCADA system to ensure proper integration of the new
instrumentation, enabling accurate real-time monitoring and control of the
water distribution system.
Project
Location – Abu Dhabi
Client
– ALDAR
Main
Contractor – Nurol LLC OPC
Scope of Works Includes
Civil & Electro-mechanical Works:
Mechanical Works: Supply and installation of
HDPE potable water networks with pipe sizes ranging from 80mm to 300mm,
including associated fittings such as tee valve chambers, flow meter and flow
control valve chambers, washout and air valve chambers, electromagnetic flow meters
within flow meter chambers, ductile iron pipes, accessories, and fire hydrants.
Electrical Works: Supply and installation of
sector measuring points, including GRP sector metering kiosks, along with all
associated cabling and earthing works.
Civil Works: Excavation, sand bedding, backfilling,
concrete encasement for road crossings, in-situ casting of valve chambers, pull
box chambers, and protection slabs.
Project
Location – Ruwais Port
Client
– Abu Dhabi Ports Group
Main
Contractor – Al Ryum Cont. & General Transport LLC
Scope of Works Includes
Electro-mechanical & Instrumentation Works
Electrical Works: Supply, installation,
testing, and commissioning of MCC panels, distribution boards, control panel
earthing systems, and associated cabling.
Instrumentation Works: Supply, installation,
testing, and commissioning of programmable logic controllers (PLCs), SCADA
workstations, electromagnetic flow meters, pressure transmitters, flood
detection systems, float switches, level transmitters, and instrumentation
cabling.
Mechanical Works: Supply, installation, testing, and
commissioning of submersible pumps, penstocks, macerators, ductile iron (DI)
pipes and fittings, valves, Jib cranes, and surge vessels.
Project
Location – Abu Dhabi
Client
– ALDAR
Main
Contractor – Nurol LLC OPC
The electro-mechanical works involved the supply and
installation of potable water and irrigation networks using ductile iron (DI)
pipes and fittings, with pipe sizes ranging from 80mm to 600mm. The scope
included the installation of valves, line valve chambers, tee valve chambers,
flow meter and flow control valve chambers, washout and air valve chambers, 14
electromagnetic flow meters housed within dedicated chambers, and 791 fire
hydrants. The electrical works comprise the supply and installation of sector
measuring points, including GRP sector metering kiosks, along with associated
cabling and earthing works
Project
Location – Al Ain
Client – Musanada /AADC
Main
Contractor – BATCO
The works consisted across storm water network and
pumping station included the installation of ductile iron (DI) pipes up to
DN500mm in size, along with valves and related accessories for the storm water
pumping station and associated external works. Electromechanical works
encompass pumps, MCC with automatic transfer switches (ATS), generators, flow
meters, valves, DI piping, and GRP piping systems. Electrical works involved
the installation of MCC panels, ATS units, generators, and associated cable
laying. Mechanical works cover the installation of DI pipes and fittings,
valves, flow meters, and pumps.
Project
Location – Madinat Zayed, Abu Dhabi
Client
– TRANSCO
Main
Contractor – METITO
The works consisted of fabrication and installation of
cast iron (CI) piping and pumping station works. For the potable water network,
the project involved fabrication, welding, and installation of carbon steel
piping for water distribution pipelines, along with equipment installation at
the pumping station. The work included carbon steel pipework up to 1600 mm in
diameter, a 100 m³ surge vessel, and horizontal split case pumps.
Project Location – Delma
Island
Client – Abu Dhabi Ports
Main Contractor - NMDC
The works consisted of
electrical and street lighting installations. This involved the supply and
installation of 14-meter-high light pole with single-arm LED luminaires,
complete with required foundations and accessories. Electrical works cover all
associated low-voltage (LV) cable networks from the substation, feeder pillars,
SLCC, and street light control cabinets, including solar timers and earth pits.
Project Location - Jubail
Island Abu Dhabi
Client – Jubail Island
Investment Company
Main Contractor - NMDC
The works consisted of electromechanical
and infrastructure utilities. For the potable water network, the project
involved supply, installation, testing, and tie-in of a DN225 main HDPE
pipeline, using butt fusion welding and horizontal directional drilling to
relocate the existing line. Works also included installation of ductile iron
fittings inside valve chambers, isolation gate valves, air release valves, and
removal of the existing HDPE pipeline. Electrical works covered the relocation
of the electrical network, including installation of uPVC cable ducts in
trenches and laying of 11 kV cables with joints and terminations.
Project Location – Dubai
Client – EXPO 2020
Main Contractor
- Spacemaker
The works consisted of
electro-mechanical and utilities installations. For the Operations Pavilion,
MEP works involved the supply and installation of MDB, SMDB, FDB panels,
cables, lighting fixtures, switches, sockets, sanitary fittings, earth pits,
earth rods, and accessories for MDB, SMDB, capacitor banks, and the building
earthing system. The potable water system included supply and installation of
uPVC and PPR piping along with water meters. The drainage network covered the
supply and installation of uPVC drainage pipes and precast manholes.
Project Location – Fujairah
Client – Sharm Fujairah Real Estate
Main Contractor - BATCO
The works consisted of
comprehensive electro-mechanical and instrumentation works across potable
water, sewerage, and irrigation pumping stations. For the Potable Water Pump
Station, the scope covered installation of pumps (210 m³/hr at 6 bar), ductile
iron piping, valves, fittings, and a pressure vessel, along with electrical and
instrumentation works including distribution boards and cable laying. The Sewerage
Pumping Station involved installation of pumps (321 l/s at 18 m head), ductile
iron piping, valves, fittings, a lifting davit, macerator, and a 160 m³/hr
odour control unit, as well as MCC panels, distribution boards, and
instrumentation cabling. For the Irrigation Pumping Station, works included
installation of pumps (48 l/s at 40 m head), DI piping, valves, fittings, and a
1400 GPM irrigation filter, along with associated MCC panels and electrical
distribution systems.
Project Location - Fujairah
Client – Ministry of Infrastructure
Development
Main Contractor
- BATCO
The works consisted
of supply, installation, testing, and commissioning of storm water pumping
stations and associated mechanical, pipeline, and electrical works.
Storm Water Pumping
Stations: Installation of three pumping stations equipped with submersible
pumps—eight units with a capacity of 832.7 m³/hr and four units with a capacity
of 643 m³/hr. The scope also includes discharge pipeline works using GRP piping
(up to DN700), installation of penstocks (DN600, DN800), gate valves,
non-return valves (NRVs), and level instruments.
Sewerage Network: Installation
of GRP sewer pipes (up to DN700), manholes, and connection to existing sewer
manholes.
Electrical and
Electromechanical Works: Installation of systems for three substations,
including MCC panels, main distribution boards (MDs), capacitor banks, and
power cables ranging from 4C x 10mm² to 1C x 630mm². Additional works include
small power systems, air conditioning, NOVEC firefighting systems, and fire
alarm systems for the substation buildings.
Project Location - Saadiyat Island
Client – TDIC
Main Contractor - Nurol LLC
The project
encompasses the execution of comprehensive infrastructure utilities, including
irrigation, sewerage, pipeline relocation, and metering systems.
Irrigation Network: Supply,
installation, testing, and commissioning of HDPE pipelines (up to 630mm
diameter) using the open-cut method, and installation of a 630mm HDPE sea
crossing pipeline (700 meters) via Horizontal Directional Drilling (HDD), using
butt fusion welding. Electromechanical chamber works include Ductile Iron pipes
and fittings, gate valves, air release valves, flow meters, washout valves,
flow control valves, and accessories.
Pipeline Relocation: Supply,
installation, testing, and tie-in works for DN250 HDPE main pipeline using butt
fusion welding for the relocation of an existing line. Works include DI
fittings inside valve chambers, isolation gate valves, air release valves, and
removal of the existing pipeline.
Metering System: Supply
and installation of flow meters up to DN500 in size.
Sewerage Network: Installation
of a 315mm HDPE sewer force main using butt fusion welding and associated valve
chambers. Installation of GRP and uPVC gravity pipelines (up to DN1400 and
depths of up to 12 meters) between manholes, including tie-in works to the
existing STP plant using the Non-Disruptive Method (NDM) for DN1400 pipeline.
Client – Dubai Aviation
Engineering Projects Corporation
Project Location - Al
Maktoum International Airport
Main Contractor - Spacemaker
Dubai
The works consisted of
supply and installation of Form 2 SMDBs, along with the supply, installation,
testing and commissioning of Form 4b, Type-6 SMDBs. The works also covered
associated LV cable installations. Additionally, the scope includes the supply
and installation of a gate barrier system for parking management.
Project Location – Upper
Zakum Central Island
Client – ZADCO
Main Contractor
– Spacemaker
The works consisted of supply
and installation of a complete drainage network consisting of uPVC pipes and
fittings in accordance with BS EN 1401-1, with sizes up to 315mm, along with
precast concrete manholes. For the potable water network, the works involved
the supply and installation of uPVC pipes and fittings as per BS 3505
standards, up to 200mm in diameter, including the installation of pumps and a
pressure vessel. The electrical works covered the supply and installation of
Main Distribution Boards (MDBs), Sub Main Distribution Boards (SMDBs), as well
as associated power and earthing cable networks and the complete earthing
system.
Project Location – Upper
Zakum South Island
Client – ZADCO
Main Contractor
- Spacemaker
The works consisted of supply
and installation of uPVC pipes and fittings up to 315mm in diameter, along with
the installation of precast concrete manholes for the building’s external
drainage system. For the potable water network, the works involved supplying
and installing uPVC pipes and fittings (as per BS 3505) ranging from 50mm to
200mm in diameter, including pumps and a pressure vessel. Additionally, the
scope covers the supply and installation of a kitchen hood and chequered plates
as part of the kitchen modification works.
Project Location - Upper
Zakum West Island
Client – ZADCO
Main Contractor
– Spacemaker
The works consisted of
supply and installation of uPVC pipes and fittings for the drainage network, in
accordance with BS EN 1401-1, with pipe sizes up to 315mm, along with precast
concrete manholes. For the potable water network, the works involved the supply
and installation of uPVC pipes and fittings as per BS 3505 standards, with
sizes up to 200mm, including associated pumps and a pressure vessel. The
electrical works covered the supply and installation of Main Distribution
Boards (MDBs), Sub Main Distribution Boards (SMDBs), power and earthing
cabling, as well as the complete earthing system.
Project Location - Upper Zakum Central Island
Client – ZADCO
Main Contractor
- Spacemaker
The works consisted of
supply and installation of uPVC pipes and fittings for the drainage network,
complying with BS EN 1401-1 standards, with sizes up to 315mm, along with
precast concrete manholes. For the potable water network, uPVC pipes and
fittings are supplied and installed as per BS 3505 standards, with sizes up to
200mm, including pumps and a pressure vessel. The irrigation network involved
the supply and installation of uPVC pipes and fittings, also in accordance with
BS 3505, up to 200mm in size. Sewer lifting station works covered mechanical
and electrical installations, including pumps, valves, pipelines, and
low-voltage panels. Electrical works comprise the supply and installation of
Main Distribution Boards (MDBs), Sub Main Distribution Boards (SMDBs), power
and earthing cabling, and complete earthing systems.
Project Location - Upper
Zakum Central Island, West Island, South Island and North Island
Client – ZADCO
Main Contractor – Spacemaker
(Central, West & South Island) &
Leighton Contracting Abu Dhabi (North Island)
The scope of works comprised
comprehensive utility infrastructure installations. It included the drainage
network, involving the supply and installation of uPVC pipes and fittings (BSEN
1401-1, up to 315mm in diameter) and precast concrete manholes. For the potable
water network, the works cover the supply and installation of uPVC pipes and
fittings (BS3505, up to 200mm), along with the installation of pumps and a
pressure vessel. The irrigation network involves the supply and installation of
uPVC pipes and fittings (BS3505, up to 200mm). Additionally, sewer lifting
station works include the mechanical and electrical installation of pumps,
valves, pipelines, and LV panels. The electrical scope includes the supply and
installation of MDBs and SMDBs, as well as associated power and earthing
cabling works.
Project Location - Mafraq, Abu Dhabi
Client – SEHA
Main Contractor - Al Habtoor
Leighton Murray & Roberts
The Irrigation Feeder
Network scope included comprehensive electromechanical works for the irrigation
system. This involved the supply, installation, testing, and commissioning of
HDPE main pipelines (up to 400mm diameter), along with ductile iron (DI)
fittings, valves, and flow meters installed within valve chambers. The scope
also covered the installation of a control panel for the irrigation system, GRP
kiosks to house the flow meters, and all associated cable interconnections
required for system operation and monitoring.
Project Location - Hail
Island
Client – ADNOC
Main Contractor - NMDC
Abu Dhabi
The scope of works comprised
comprehensive utility infrastructure installations. It includes the drainage
network, involving the supply and installation of uPVC pipes and fittings (BSEN
1401-1, up to 315mm in diameter) and precast concrete manholes. For the potable
water network, the works cover the supply and installation of uPVC pipes and
fittings (BS3505, up to 200mm), along with the installation of pumps and a
pressure vessel. The irrigation network involves the supply and installation of
uPVC pipes and fittings (BS3505, up to 200mm). Additionally, sewer lifting
station works include the mechanical and electrical installation of pumps,
valves, pipelines, and LV panels. The electrical scope includes the supply and
installation of MDBs and SMDBs, as well as associated power and earthing
cabling works.
Project Location – Saadiyat Island, Abu Dhabi
Client – TDIC, Consultant
– CHSS
Main Contractor - NUROL
The Electromechanical
works comprise the complete scope for multiple systems. The Ventilation System
includes the supply, installation, testing, commissioning, and maintenance of a
Tunnel Ventilation System equipped with 20 Jet Fans, along with all required
cabling, control panels, and SCADA interface integration. The Drainage Network
with Pumping Stations covers the supply, installation, testing, commissioning,
and maintenance of storm water pumping stations, featuring 7 submersible pumps.
The Electrical Works
scope involves the supply and installation of control panels for both the
drainage and ventilation systems, including necessary cable laying and
terminations. The Mechanical Works include the supply, installation, testing,
commissioning, and maintenance of two storm water pumping stations, with
submersible pumps (7 Nos) and associated stainless steel piping (up to DN350)
complete with valves and non-return valves (NRVs).
Additionally,
Instrumentation and SCADA Interface Work involves the supply and installation
of ultrasonic level transmitters, float switches, and limit switches for
valves, with full integration of instruments into the SCADA system.
Project Location – Upper Zakum North Island
Client - NMDC
Main Contractor - Spacemaker Abu Dhabi
The infrastructure utilities
work consisted of Drainage Network, involving the supply and installation of
uPVC pipes and fittings conforming to BSEN 1401-1, with pipe sizes up to 315mm,
and the installation of precast concrete manholes. For the Potable Water
Network, the works cover the supply and installation of uPVC pipes and fittings
as per BS3505, with sizes up to 200mm, along with pumps and a pressure vessel.
The Electrical Works scope includes the supply and installation of Main
Distribution Boards (MDBs) and Sub-Main Distribution Boards (SMDBs), as well as
associated power and earthing cable networks and earthing systems.
Client – EMAL
Project Location - Taweelah, Abu Dhabi
Main Contractor - Larsen and Toubro
The works consisted of
Pipeline Fabrication, Welding, and Installation comprising the supply,
fabrication, welding, installation, testing, and commissioning of Carbon Steel
(CS) piping up to DN600, Stainless Steel (SS) piping, and HDPE piping along
with necessary fittings, accessories, and painting works. These installations
support the potable water system, cooling water system, and pressurized air and
gas lines for both existing and new cast house facilities. Additionally, the
scope includes the relocation of HDPE pipelines for the potable water network
with pipe sizes up to DN300.
Project Location - Arzanah Island
Client – ZADCO
Contractor - ADMMI
The electromechanical works
involved the supply and installation of the fuel pipeline, GRP cable trays,
earthing system, and 13.8kV cable laying, along with testing and commissioning
of medium voltage (MV) cables.
Project
Location – Taweelah Abu Dhabi
Client
– EMAL
Main Contractor – Consolidated
Contracting Engineering
The works consisted of installation across various
networks: Storm water and drainage networks with RCC pipes up to DN2000 and
UPVC pipes up to DN600, including all necessary tie-ins and manhole
connections. Sanitary sewage networks involve installing UPVC pipes up to DN250
with connections to existing systems and manholes. Fire water networks cover
the installation of FRP pipes up to DN300, carbon steel pipes with welding,
wrapping, valves, and fittings. Potable water networks include installation of
HDPE pipes (SDR9) up to DN300 and fittings. Pressurized sanitary sewage systems
involve UPVC pipes and fittings up to DN200, including valves, tie-ins, and
manhole connections. Pumped storm water works include UPVC pipes and fittings
up to DN300 with valves and system tie-ins. Permeate service water systems
consist of SDR 9 HDPE pipes and fittings up to DN300 with valves and
accessories. Compressed air and natural gas networks involve carbon steel
piping with welding up to DN600. Lastly, utility road crossing duct works
include installation of UPVC road crossing ducts up to DN400 in size.
Project Location - Al
Ain
Client – TRANSCO
Main Contractor - Torishima
Pump Mfg. Co
The works consisted of
pipeline fabrication, welding, and installation for the potable water
distribution network. This includes fabrication, installation, and testing of
FBE-coated carbon steel pipes and fittings up to 2200mm in diameter (supplied
by the client). The work involves field welding of pipe joints, non-destructive
testing (NDT) of the welds, and holiday checks on the carbon steel pipes to
ensure coating integrity.
Project Location - Yas
Island, Abu Dhabi
Client – ALDAR
Main Contractor - Taisei
Corporation
The scope of
electromechanical works includes the Tunnel Ventilation System, encompassing
the supply, installation, testing, commissioning, and maintenance of 40 jet
fans, along with all necessary cabling, control panels, and SCADA interface for
system automation. The drainage network comprises the complete setup of three
storm water pumping stations, which includes 16 submersible pumps, stainless
steel pipework (up to DN350), valves, non-return valves (NRVs), level
instruments, and flow meters for automatic tunnel drainage operation. The
system also includes the connection of discharge lines to the existing drainage
system via oil interceptors and bar screens. The electrical works involve the
supply and installation of control panels for both the drainage and ventilation
systems, as well as all associated cable laying and termination. Additionally,
the instrumentation and SCADA interface scope includes the supply and
installation of ultrasonic level transmitters, float switches, limit switches
for valves, and integration of all instrumentation with the SCADA system.
Project Location - Al
Ain
Client – TRANSCO
Main Contractor - ASTRACO
Construction
The works consisted of
instrumentation and SCADA interface work along with electromechanical tasks.
This involves the supply, installation, testing, and commissioning of control
valves and an RTU shelter equipped with distribution boards (DB, SMDB, UPSDB)
and an A/C sequence panel for remote SCADA operation. Additionally, the work
covered the supply and installation of flow meters up to DN400 in size, along
with other associated instrumentation.
Project Location - Yas
Island, Abu Dhabi
Client – ALDAR
Contractor - ENVAC Middle
East
The works consisted of
pipeline fabrication, welding, and installation works includes the installation
of 5.89 km of 3LPE-coated mild steel pipelines for the automated waste
collection system on Yas Island. This involved fabrication, fit-up, and welding
activities. Additionally, a cathodic protection system is installed along 13.3
km, with exothermic welding of anodes at every 150 meters. Trench excavation
works cover 4.6 km for laying the MS refuse pipes, including bedding, sand
surrounding, compaction, warning tape installation, backfilling, and removal of
surplus excavated material off-site. The project also includes the construction
of 21 manholes with excavation works for inspection and maintenance of the
waste collection system.
Project Location – Dubai
Client - Nakheel
Main Contractor - Taisei
Corporation Dubai
The electromechanical works
consisted of both mechanical and electrical tasks, including the supply and
installation of cables and light fittings. The scope also includes the
installation of a penstock measuring 2800x1600mm, a 1600mm duckbill check
valve, GRP pipes and fittings up to 1800mm in diameter, along with the
associated civil works.
Project Location – Dubai
Client – Nakheel
Contractor - Taisei
Corporation
The works consisted of storm
water drainage network works include earthwork excavation for pipe laying,
including bedding, sand surrounding, warning tape installation, backfilling,
compaction, and removal of surplus material. The scope also covers the
installation of GRP pipes with diameters of 400mm, 1400mm, and 1600mm in
trenches, including GRP lamination joints.
Project Location - Yas Island, Abu Dhabi
Client – ALDAR
Contractor - Taisei Corporation
The works consisted of electrical
works for bridges BC-3, BC-4, BC-5, BC-7, and BC-8 include the supply and
installation of cables, junction boxes, and support systems. The scope covers
the installation of 108 light poles and bridge lights, 3,942 meters of 6-way
telephone ducts, and 1,902 meters of 6-way 22kV cable ducts (DN200).
Additionally, navigational lights, day markers, and control panels are supplied
and installed. The works also include the supply and laying of cables up to
16mm² over 6,050 meters and PVC conduits up to 100mm diameter totaling 3,170
meters.